Budget
Compare the original budget with actual cost, pending bills and projected cost for a project.
Planned Against Actual
Open a project and select Budget. It is read-only: it fills from your estimate, bills and change orders. Use Expand All to open every section.
Budget
Search budget items...SectionExpand All
NameOriginalActualDifferenceProjected CostCompleted
EstimateRM 4,200,000RM 1,850,000RM 4,200,00044%
03 — ConcreteRM 980,000RM 1,040,000RM 1,040,000100%
AllowancesRM 150,000RM 42,000RM 150,00028%
Grand TotalRM 4,350,000RM 1,892,000RM 4,350,00043%
Original Budget
RM 4,350,000
Actual Cost
RM 1,892,000
Pending Bills
RM 215,000
Paid Invoices
RM 1,892,000
Projected Total
RM 4,410,000
- 1Search and Section · Estimate, Allowances, Change Orders
- 2Expand All · or Collapse All
- 3Section row · cost codes sit under it
- 4Difference · red when over budget
- 5Completed · Actual against Original
- 6Footer totals
Actual vs Pending Bills
Actual counts paid amounts only, including partially paid bills. Pending Bills is the amount still due on pending, approved and overdue bills. Projected Cost is the higher of Original and Actual.
Needs an estimate first
Until the project has an estimate or Bill of Quantities, Budget shows "You have no financial information yet". Budget uses the same access as Reports.