Docs
Schedule

Schedule

Import project schedules, visualise them on an interactive Gantt chart, and track progress against the critical path.

What is the Schedule?

The Schedule module is where your project's timeline lives. Import a programme from Primavera P6 and Bestrack turns it into an interactive Gantt chart — showing every activity, dependency, and milestone, with the critical path highlighted so you always know what can't slip.

Schedule is found inside each project. Open any project from your dashboard and select Schedule from the sidebar to get started.

Click "Schedule" to expand · Then click any stage to see details

Importing a Schedule

Bestrack accepts XER files — the standard export format from Primavera P6.

  1. In Primavera, export the project as an XER file
  2. In Bestrack's Schedule page, click Import and upload the file
  3. Bestrack parses the file and builds the Gantt view automatically

The import brings in every activity along with its WBS code, start/finish dates, duration, predecessors/successors, and activity type.

Gantt Chart View

The Gantt chart is the primary view. Each row is an activity; the bar shows its position and duration on the timeline.

ElementWhat it shows
Task barStart, finish, and duration of the activity
ArrowsDependency links between activities
Red barActivity on the critical path
Progress fill% complete on the bar itself
DiamondMilestone (zero-duration activity)

Zoom: Switch between Day, Week, Month, and Quarter timescales from the toolbar — Day for close detail, Quarter for the full programme at a glance.

Columns: Choose which columns to show on the left-hand table (Activity ID, Name, Start, Finish, Duration, % Complete).

Tasks and WBS

Activities are organised under the Work Breakdown Structure (WBS) from the imported file — a hierarchy of phases, sub-phases, and individual tasks.

Click the arrow on any WBS group to expand or collapse it. Use the Expand All / Collapse All button in the toolbar to toggle every level at once.

Each activity carries:

  • Activity ID — unique identifier (e.g. A1000)
  • Name — activity description
  • Type — task, start milestone, or finish milestone
  • Duration — planned days to complete
  • Dates — start, finish, and due date
  • Assignee — project team member responsible
  • Float — total and free float, measuring schedule slack

Dependencies and Critical Path

Dependencies connect activities so that one must happen before another. Bestrack supports the four standard relationship types — click any to see what it means and when to use it.

Click "Dependency Types" to expand · Then click any type to see details

Every link can also include a lag (a fixed delay in days) between the two activities, so you can model curing times, approval gaps, or any enforced waiting period.

The critical path is the longest sequence of dependent activities — any delay on these tasks delays the whole project. Bestrack flags critical activities automatically so you can see what to protect.

Progress and Versions

Tracking progress: Update an activity's % complete directly on the Gantt chart. Dragging the progress edge of a task bar updates the value live. Float days show how much slack an activity has before it becomes critical.

Versions and baselines: A schedule can have multiple versions — typically a baseline plus one or more working revisions. Use the version selector at the top of the page to switch between them and compare progress against the original plan. One version is set as the active programme at any time.

Use Refresh in the toolbar to reload the latest data and pick up changes made by other team members.